P-02 — Design foundation · 2026 · in study
Ñande Roga
A series, not a building. Heavy — brick — breathing.
Vision
[ 01 / 11 ]Ñande Roga — "Our House" in Guaraní — is a repeatable housing series, not a building: a fixed kit of parts, a designation, a product line of dwelling for the Paraguayan urban edge. It adopts the grammar of the Soviet housing series — fixed bay, cross-wall plan, panel nomenclature, assembly as scheduled event — and re-founds it in local material and local hands: confined clay brick, prestressed clay-block floors, stabilized earth, and a rationed quantity of concrete.
A heavy, repeatable housing machine in Paraguayan clay — Soviet in its grammar, Guaraní in its ground — that shades deeply, breathes freely, and can one day be taken apart into the bricks it was born from.
Phase I delivers 480 dwellings (~33,000 m² residential GFA) on 2.5–4 ha at the urban edge of Greater Asunción: three 5-storey bars and one 8-storey portal slab, every dwelling double-aspect, shaded by a 2.0–2.4 m galería, raised on a 1.5 m loma plinth. The performance claim is falsifiable — ≥ 90% of occupied hours in adaptive comfort on passive strategies alone — gated on simulation, a mockup cell, and one full year of post-occupancy measurement.
Design principles
[ 5 BINDING ]-
01
The Series, not the Building 3.9 × 7.2
One structural bay, one cross-wall system, one facade panel family; three unit types (≈ 42 / 56 / 70 m²) cut from the same grid. Nothing exists once; nothing custom that can be repeated.
-
02
The Galería-Street 2.0–2.4 m
The Soviet internal street and the Paraguayan galería fused into one recessed element: shade, rain protection, circulation, and the physical seat of collectivity.
-
03
Mass inside, air through ≥ 20 ACH
Loadbearing brick and rammed-earth walls as thermal battery, contractually coupled to cross- and stack-ventilation. Mass without night flush is a liability in the humid subtropics; the coupling cannot be value-engineered apart.
-
04
The Loma Plinth +1.5 m
The ground lifted on confined-masonry piers: capillary break, flood datum, the vernacular loma of Asunción at district scale. The plinth level is never dwelling; it is the common ground floor.
-
05
The Block as Material Bank 100 YR
Lime mortars for brick reclamation, rubble re-pressed into stabilized-earth blocks, excavation reused in rammed walls, tacuara grown on site as facade reserve. On Paraguay's hydro grid, embodied carbon is the entire carbon story; the building is a deposit, not a destination.
Site & urban strategy
[ FASE I ]The search image is a 2.5–4 ha urban-edge parcel in Greater Asunción's expansion belt (Luque, Capiatá, Mariano Roque Alonso, Lambaré fringe): flat to gently sloping (0.5–3%), alluvial silty-clay with a wet-season water table at 0.8–2.5 m, above the five-year flood line, long axis available E–W, open to the northeast breeze, with a trunk bus corridor on one edge and school and health post within 800 m. Clear tenure, grid electricity and piped water at the boundary are prerequisites; absence of sewer is assumed and designed for. High water table and termite pressure are generators, not objections: no basements, shallow footings, ventilated timber, funded inspection.
Phase I places three 100 m E–W bars (B1–B3, 5 storeys, 360 dwellings) and one 8-storey N–S portal slab (B4, 120 dwellings) whose gable — the Guaraní relief mural in projected brickwork — faces the bus street. Dwelling faces inward; monument faces out. N–S calles de viento between the bars funnel the prevailing breeze into two ~100 × 38 m courtyard gardens, which keep 20+ m of winter noon sun against the 16 m bar shadow. A plaza with the preserved timbó canopy, fútbol court and tereré tables sits at the portal; a ~1,200 m² retention lagunita occupies the low west corner, deliberately downwind of intake air. Coverage ≈ 17% · FAR ≈ 1.0 (headroom to 1.6) · 133 dwellings/ha net · ~450 inhabitants/ha. Full build-out: a mikrorayon of ~1,400 dwellings in three phases around a school-and-park spine.
Every level is reachable dry-foot in the rain — plinth, portal and galería form one covered line. The motorcycle is the primary vehicle of the Paraguayan working household: 1.2–1.5 per unit → 600–700 covered bays in the plinth arcades and two moto patios. Cars get their honest minority share — 0.3–0.35 per unit → ~160 edge-field surface bays in porous rubble pavers under trellis, never in the courtyards, 10% EV conduits. ~480 bicycle racks; bus stop ≤ 200 m from every gate; remise and moto-taxi rank at the portal. The internal loop is a shared-surface calle tranquila at 20 km/h, pedestrian priority on the plinth. No garage: buried parking for 480 units would cost more than the blokera, the guardería and the lagunita together — and we choose the places people live in.
Program — Fase I · 480 units · mix 20 / 45 / 35%
| Facility | Area | Role |
|---|---|---|
| Casa comunitaria | 350 m² | double-height in the portal — the social condenser |
| Guardería | 260 m² | ~50 children, courtyard-facing |
| Sala de salud | 100 m² | first-aid post |
| Cocina comunitaria + horno de barro | 120 m² | the clay oven as declaration of settlement |
| Cooperative office + maintenance depot | 90 m² | the Three Clocks run from here |
| Blokera — rubble re-pressing workshop | 200 m² | demolition rubble becomes the next building |
| Vivero — tacuara + native nursery | 300 m² | the facade reserve grows on site |
| Lavaderos + tendales | 400 m² | communal wash-yards and drying lines, open air |
| Bodegas, bicycle, moto storage | 400 m² | under plinth arcades |
| Commercial band — street edge | 1,400 m² | 10–14 premises: almacén, panadería, farmacia, repair |
Climate strategy
[ PASSIVE ONLY ]Baseline: 35–38 °C summer maxima at 70–85% RH · ~1,400 mm/yr with 80–100 mm/h cloudbursts · mild winter (11–13 °C means, surazos to 5–8 °C) · NE prevailing breeze. At 25.3°S the north facades are the sun side, the south facades the cool side. Bars run long-axis E–W; large glazing never faces the rising or setting sun. The 2.0–2.4 m recess is a fixed solar instrument: summer noon sun at 88° — fully shaded; equinox 64.7° — 1.3 m ray run, short of the recess; June solstice 41.3° — a 0.7–1.1 m sun band enters and warms the brick floor exactly when wanted. ~95% of annual beam hours are blocked from north glass; free winter gain is admitted. Wing walls deflect the oblique NE breeze; the portal slab wears the celosía against low E/W sun; the bars mass to the SW against the surazo.
Cross walls (~350 kJ/m²K, 6–8 h lag) and rammed-earth commons (~500 kJ/m²K, 8–10 h lag, hygric buffering) stand exposed behind lime finishes; slab soffits are exposed — suspended ceilings are banned in living areas; roof insulation sits outside the slab. 25–30 t of cycled material per unit absorb 20–30 kWh per diurnal swing, flattening a 12–14 °C outdoor swing to ~4 °C indoors. Every unit is double-aspect with ribbon openings ≥ 5% of floor area per aspect and fixed brick-louvre vents over the doorheads: cross-flow ≥ 20 ACH on breeze days. Brick shafts (0.6 × 1.2 m, one per two bays) extract kitchen and bath air at source, ≥ 40 L/s per dwelling; the night purge ≥ 8 ACH recharges the mass with courtyard air 1–2 °C cooler than street air.
The bar section is itself the overhang — driving-rain exposure on glazing is near zero. Humidity is controlled by source extraction, breathable monolithic walls and ventilated cavities; mold is an airflow-geometry problem, not a dehumidifier problem. Continuous ribbon bands with splayed lime-washed reveals target a 3–5% daylight factor in living rooms and daylight autonomy to dusk; no decorative exterior lighting — the building is a shadow in the evening.
Roof yield ≈ 8,400 m³/yr against ≈ 8,700 m³/yr non-potable demand — near parity. Gate: WUFI transient runs of every build-up — surface RH < 80% for ≥ 95% of hours. Verification: EnergyPlus + CFD for the courtyard and calle-de-viento field, and twenty instrumented units through one full year before the claim publishes as measured.
Declared comfort targets — passive only, adaptive comfort 80%
| Metric | Target |
|---|---|
| Occupied hours in adaptive comfort | ≥ 90% |
| Heat-wave design day 36–38 °C | indoor peak ≤ 32 °C — fan covers residual |
| Night recovery after hot day | ≤ 27 °C by 23:00 |
| Surazo 8 °C, rain | ≥ 17 °C indoor — zero active heating |
| Overheating hours > 30 °C operative | < 3% annual |
| Air movement | ≥ 20 ACH day cross · ≥ 8 ACH night purge |
Structural & modular system
[ 12 PARTS ]Transverse confined-masonry cross walls (230 mm 18-hole clay brick, f'm ≥ 8 MPa) at 3.9 m centres, confined by 180 mm cast-in-place tie columns and bond beams at every floor; one-way prestressed-joist and clay-bovedilla floors spanning 3.9 m with a 45 mm topping; cross walls acting as shear walls in both directions. The 8-storey portal slab switches to an RC frame with brick infill bracing the lower two stories — honest engineering at Paraguay's seismicity. Material ration per m² GFA: concrete ≤ 0.16 m³ · steel ≤ 22 kg · brick ≈ 120 units.
All precast elements weigh ≤ 2.0 t — liftable by a single 12 t mobile crane; no tower crane exists in the program. Every panel derives from one 3.9 × 1.35 m half-storey mold cell: one formwork family with bolt-in inserts produces the entire facade catalog. Each part number is optimized once (FE layout, joist spacing, tie section) and repeated ~4,000 times across the quarter — savings come from series multiplication, exactly the Soviet logic. 30% recycled brick aggregate in non-structural mixes; excavation reused in rammed walls.
Foundations — no basements, no deep piles by default: 400 mm recycled-brick rubble trench footings under every loadbearing wall (capillary break, drainage blanket and circularity in one element); 1.5 m confined-masonry plinth piers at 3.9 m centres carrying ground beams; a ventilated rubble crawl, never sealed. Under the 8-storey portal only, geotech-gated options: vibro-rubble columns or 1.5–2 m over-excavation with lime-stabilized backfill on a stiff ground-beam grid.
Series catalog — ÑR-6 part numbers
| Code | Element | Module | Weight | Material |
|---|---|---|---|---|
| П-1 | Cross wall lay-unit — site-laid, confined ties | 3.9 × 2.7 m | hand-set | 230 mm brick, lime plaster |
| НС-1 | North facade rain-screen, window band | 3.9 × 1.35 m | ≤ 0.9 t | brick-slip face + rubble-aggregate micro-concrete, ventilated cavity |
| НС-2 | North spandrel / celosía vent band | 3.9 × 1.35 m | ≤ 0.8 t | perforated projected brick |
| ЮС-1 | South facade panel — open band, moss zone | 3.9 × 1.8 m | ≤ 1.1 t | as НС-1, wider opening |
| ГС-1 | Galería spandrel + slab-edge fascia | 3.9 × 0.9 m | ≤ 0.7 t | board-marked micro-concrete |
| ПП-1 | Floor — joists @ 0.65 m + bovedillas + topping | 3.9 × 7.2 m | ≤ 200 kg / joist | prestressed joist + clay block |
| КР-1 | Stair flight + landing | fixed | ≤ 1.4 t | RC, rubble aggregate |
| ЦС-1 | Ventilation shaft segments | 0.6 × 1.2 × 2.7 m | ≤ 0.5 t | brick-faced precast |
| ПС-1 | Celosía screen — gables, E/W faces | 2.0 × 2.7 m | ≤ 0.8 t | projected-pattern brick |
| ПС-2 | Guaraní relief mural panels — portal gable | 3.9 × 2.7 m | ≤ 2.0 t | projected brick + rubble aggregate |
| ЖБ-1 | Cisterns, gutters, scuppers, chain anchors | misc | ≤ 0.6 t | watertight micro-concrete |
| Д-1 | Galería rails, trellis, shade frames | 3.9 m bays | — | treated timber + tacuara |
Massing & facade
[ 6.7 : 1 ]The bar reads as a 6.7 : 1 hull — ≈ 100 × 11.6 m, 15.0 m to coping, 17.5 m with stacks and tank band. The bay is a near-√2 rectangle (3.9 × 2.7 m); recess depths (2.0 / 2.4 m) and plinth height (1.5 m) all derive from it. The north face is a continuous shadow band interrupted by board-marked slab-edge fascias — five datum lines per elevation, no more; living bays notch 0.4 m deeper than bedroom bays — variation without decoration. The south face opens in wider ribbon bands toward the courtyard; gables are blind brick terminations with celosía screens to the stairs. The building's window is its shadow.
North facade — outside → in
| # | Layer | Depth / spec |
|---|---|---|
| 1 | Д-1 rail + trellis, resident planting, rain chains at bay edges | air |
| 2 | Galería floor falling to chain gutter | 2.0 / 2.4 m recess |
| 3 | НС-1/НС-2 rain screen — 90 mm brick-slip face, 12 mm open joints, 40 mm ventilated cavity, 120 mm rubble-aggregate backing | ≈ 250 mm |
| 4 | Structure — 230 mm confined brick + bond beam, soffit exposed | ≈ 230 mm |
| 5 | Lime plaster; splayed cream embocadura reveals at 45° | light amplifier |
Wall depth at openings ≈ 480 mm plus 2.0 m of shadow. Three brick tones in horizontal strata like a cut riverbank; no paint on brick. Residents own the trellis and reveal layer; rail, soffit, fascia and brick are inviolable. South spandrels are zoned for moss and fern colonization from year 5. The 1.5 m plinth is a rusticated rubble-concrete arcade — moto and bicycle storage, bodegas, lavaderos, kiosco, cooperative depot — open and inspectable, nothing sealed; its deck is a continuous raised walk, dry-foot in any storm, with brick stoops up to the galería and steps and ramps to the street at ≤ 25 m intervals. Two stair-lift cores project 0.9 m as south-face brick buttresses, daylit through celosía, discharging directly onto the galería — the galería is the corridor; no internal public corridor exists anywhere in the bar.
Stepped 2% roofs drain to oversized internal gutters with twin scuppers; each unit's water tank docks on precast saddles aligned over its shaft — the tank band as disciplined cornice. Skyline inventory fixed by design: nothing on the roof that is not also a load, a duct, or a gutter.
Construction approach
[ 26 WK / BAR ]Industrialize the vernacular: Paraguay's advantage is brick hands, a mature prestressed-joist industry, national cement and kilns everywhere — not panel factories. Off-site (≈ 25–30% of labor hours): facade panels cast face-down with brick slips pre-laid in the mold, precast stairs, shafts, gutters and cisterns, pressed stabilized-earth blocks; joists are procured from existing prestressing yards. On-site: hand-laid confined walls, slab assembly, rammed-earth commons. The plant is a 2,000 m² yard on site with one casting bed and one mold family; transport is 50–300 m flatbed moves on the future calle tranquila; buffer stock 7 days per type; storm protocol Oct–Mar — casting under shed, maturity method absorbs cure interruptions.
Sequence — typical bar
| Weeks | Activity |
|---|---|
| 0 | Yard commissioning; mockup cell proven |
| 1–4 | Earthworks (cut/fill balanced, soil banked), rubble trench footings, plinth piers + ground beams |
| 5–17 | 5 storeys × 2.5 wks — walls + ties (d1–5) → stairs + slab (d6–8) → cure overlapping next level (d9–10); facades one storey behind structure |
| 18–19 | Roof build-up, precast gutters, cisterns, tank saddles |
| 20–24 | Services rough-in, lime plaster, screeds, joinery, chains |
| 25–26 | Commissioning: cistern flush, chain + gutter test, snag, handover to cooperative |
Three bars and the portal run in staggered pairs over ~60–70 weeks with a peak workforce of ~100, including 20% apprentices from the future resident body — the yard is the district's first payroll. Quality control adopts Soviet geodesy and ОТК discipline: closed survey loops, plinth level ±10 mm over 100 m, panel ±5 mm, a frozen reference type-bay per bar, maturity-gated strikes, panels stamped with part number and cast date, non-conformance charged to the yard, not the crew. A mockup cell and one prototype bay must pass a full wet season before series production.
Cost & speed vs conventional — Class 5, to be proven on the prototype
| Lever | ÑR-6 | Effect |
|---|---|---|
| Concrete ration | 0.16 vs ~0.32 m³/m² | −45–50% on the most expensive material |
| Formwork | 1 mold family × ~600 reuses | formwork cost per element → near zero |
| Facade labor | face pre-cast, no scaffold | facade package −30–40% |
| Cranes | 1 × 12 t mobile | mobilization −60% |
| Duration | 26 vs 40–48 wks / bar | −35–40%; earlier cooperative income |
| Waste | excavation + rubble reused | 10–15% vs 25–30% |
| Whole building | ≈ US$ 540–680/m² | −18–25% vs baseline US$ 700–850/m² |
The saving exists only at series multiplication — ≥ 3 bars, the molds must pay for themselves — and the maintenance advantage accrues over decades, not at handover. The claim is falsifiable by design: the prototype carries the cost model before a single production brick is laid.
Sustainability & impact
[ THREE CLOCKS ]Collectivity must be load-bearing — in program, budget and maintenance clocks — or it fails; that is the Robin Hood Gardens lesson. Here it is functional: the lavadero, the clay oven, ~70 huerta plots, the blokera and the vivero are shared labor with shared product, administered by a resident cooperative with a real budget and a contractual maintenance doctrine. Each household personalizes its own 2.2 m galería bay — identity without fences; the geometric supervision of 300+ galerías over guardería, court and plaza replaces surveillance with daylight. The unit mix is family-weighted (20% one-bed / 45% two-bed / 35% three-bed); every dwelling double-aspect, no single-aspect plan anywhere in the series.
Sustainability targets
| Domain | Target |
|---|---|
| Embodied carbon | concrete ration ≤ 0.16 m³/m² (−45–50% vs baseline); 30% recycled brick aggregate; excavation fully reused; embodied carbon as the entire carbon story on the hydro grid |
| Circularity | lime mortars for reclamation; blokera re-presses rubble; building as material bank; disassembly detailed, not implied |
| Water | near parity roof yield vs non-potable demand (8,400 / 8,700 m³/yr); 180 m³ cisterns; lagunita retention; biodigester + wetland treatment |
| Operational energy | zero active heating; zero cooling equipment in base design; daylight autonomy to dusk; fans as resident backup only |
| Biodiversity | zoned colonization — south moss/fern bands, north vines; native vivero; preserved mature canopy |
| Durability | three clocks — building 100+ yr, services 15–30 yr, planting by season; breathable lime assembly, resident-repairable, no sealed systems |
Series multiplication delivers ≈ US$ 540–680/m² against a regional conventional baseline of US$ 700–850/m² — 18–25% below — with a 35–40% program shortening and earlier cooperative income. The construction year is the first social program: the yard is the first payroll, its apprenticeship the first school. Both the cost claim and the comfort claim stand or fall on the prototype and the monitoring year.
Plates
[ PENDING ]| Plate | Subject | State |
|---|---|---|
| V-01–05 | Exteriors: galería-street · shadow band · portal mural · courtyard · storm over the lagunita | Pending |
| I-01–05 | Interiors: June sun band · cross-vent axis · south bedroom · casa comunitaria · cocina + horno | Pending |
| A-01/02 | Oblique aerial masterplate · vector masterplan 1:1000 | Pending |
| D-01–06 | Details: strata macro · panel joint · sun-stripe section · plinth pier · rain chain · celosía | Pending |
| G-01–06 | Diagrams: climate · modular system · construction sequence · social life · water · ventilation | Pending |
Documents — source set
- 01Design foundation — consolidated summary — source of this page
- 02Visualization brief — render log and prompts — section 9 of the source document
Critical open questions
[ 9 GATES ]- Q1
Site acquisition + geotech — soundings, water table, rubble-column decision. The master gate. pending
- Q2
WUFI transient runs of every wall build-up and junction — the stack-up stands or falls here. pending
- Q3
EnergyPlus + CFD courtyard / calle-de-viento field against the 4 °C claim. pending
- Q4
Mockup cell + prototype bay through one full wet season — all pass/fail gates. pending
- Q5
Class 5 → Class 4 cost model on prototype procurement. pending
- Q6
Planting palette — regional species verification and invasive-law check. pending
- Q7
Photorealistic visualization pass — the project is currently untested in image. pending
- Q8
Code package: fire strategy, acoustics, local energy code mapping. unstarted
- Q9
Post-occupancy: 20 instrumented units, one full year, before claims publish as measured. pending
Bottom line
[ 11 / 11 ]A complete, internally consistent design foundation for a repeatable Paraguayan housing series — heavy, brick-built, climate-first, economical by multiplication — ready for its site, and honest about what the site will change.
Free release download
This project is released as a free design study under the controlled
delivery system. A zero-price order creates an instant entitlement; the
buyer receives a raw capability once via the order-confirmation page.
That capability must be sent through the
Authorization: Bearer header when fetching
order status or initiating a download. The server validates the
SHA-256 hash of the capability against the stored value; a mismatch
reveals no order information. Download tokens generate short-lived
signed R2 URLs (mock delivery in the current phase; production R2
delivery pending).
How to download: complete the zero-checkout flow for this
project; the raw capability will appear in the order-confirmation HTML.
Copy it and use it in the Authorization header for
subsequent requests. Capabilities in query strings are rejected.